In the 1940s, the Oak Ridge fuel distribution plant was built in an unprecedented secret as a component of the Manhattan Project, with the goal of obtaining enriched uranium for the world’s first atomic bomb and expanded its operations during the Cold War, generating enriched uranium for defense and industry ends.
Uranium enrichment operations stopped at the site in 1985 and the plant was officially closed in 1987. UCOR, a partnership run through Amentum with Jacobs, has been the site’s prime cleanup contractor since 2011. POWER interviewed Kenneth Rueter, President and CEO. , to be more informed about the paintings that took place at the site and how the informed classes can be implemented in nuclear power plant decommissioning projects.
POWER: The task is notoriously extensive. Did the cleaning effort begin without delay and continued uninterrupted?If so, what were the facets of the work that consumed the most time?Was it expected to take so long to complete or were there unforeseen delays along the way?
Rueter: In 1980, the Comprehensive Environmental Responsibility, Compensation and Response Act (CERCLA) granted broad federal authority to treat potential emissions of hazardous substances.
In 1989, two years after the plant closed in what is now known as the East Tennessee Technology Park (ETTP), the U. S. Department of EnergyThe U. S. (DOE) created the Office of Environmental Management to oversee the cleaning of hazardous fabrics at U. S. DOE facilities. But it’s not the first time Oak Ridge Reserve. After five decades of nuclear weapons production, the Cold War left 1. 5 million cubic meters of counterfeit waste and 88 million gallons of liquid waste in the DOE complex, requiring permanent and safe storage and storage. ground and groundwater at these sites, thousands of buildings and structures had to be decontaminated and dismantled.
In addition, in 1989, Oak Ridge Reserve was placed on the national precedence list, identifying it as a place to be cleaned in accordance with CERCLA provisions. Remediation paintings began at the time with Lockheed Martin Energy Systems Inc. as the main cleaning contractor. Bechtel Jacobs replaced Lockheed Martin in 1998, then UCOR became doE’s main cleaning contractor for ETTP in 2011.
The DOE learned from the outset that cleaning up the old fuel dispersion complex would be a decades-old company. From the beginning, the Department’s vision was to turn the site into a multi-purpose commercial park, moving the land for commercial procurement and task creation. .
The elements of the allocation that consumed the most time were execution in dangerous situations between infected and deteriorated structures. The constructions planned for demolition were covered with radioactive material. Years of unregulated disposal practices had contaminated soil and groundwater. The demolition of the centerpiece of the site, the construction of K-25 gas diffusion one mile long (Figure 1), the largest dismantling ever carried out in the DOE complex.
POWER: What practices can you share, i. e. in the field of decontamination and environmental cleanliness, which would gain advantages for nuclear power plant dismantling groups?
Rueter: It would probably not be transparent how dismantling applies to electricity. For us, our ability to safely close non-transparent amenities and dispose of waste without harming the public or the environment is directly related to non-transparent force generation in the United States. States and around the world, because the public and legislators will have to be convinced that our industry has the capacity to do so.
In many ways, UCOR has provided a style for the dismantling of advertising nuclear power plants in an even more harmful environment. UCOR executes elaborate plans to characterize installations, appliances, components, soil and groundwater to provide the desired knowledge to create paint plans. Plans involve in-depth analysis designed to identify hazards and put controls in place to protect personnel and the environment. Project operations and safety personnel work with suppliers to design, manufacture and acquire non-public protective appliances and other appliances that want to overpaint. Innovative approaches are also used that reduce or eliminate the need for human penetration in potentially hazardous environments.
As a learning organization, UCOR uses a transparent and timely communication technique used to inform painters and subcontractors of the various hazards they might encounter, as well as mitigation measures and corrective movements taken or planned to eliminate those hazards. The participation of technique, painting, painting, drawing plans and then painting is expected and encouraged to ensure that lessons learned are captured and implemented for long-term activities.
As the star of doE’s Voluntary Protection Program (VPP), UCOR adopts a zero-accident philosophy committed to the concept that all injuries can be prevented.
POWER: Can you count the demanding situations the allocation team has faced and how they have been overcome?
Rueter: There have been many demanding express situations over the decades, but 4 capture the main obstacles encountered in the D
The first challenge was synchronization. Construction of the K-25, the cornerstone of the five-factories procedure, was closed in 1964, but dismantling activities did not begin until 2002. The elapsed time, some 38 years, has had a negative effect on the structure. . A general roof failure resulted in a significant intrusion of water that continued around deactivation, which affected the surroundings of general paints with waterfalls and water of annoying state by the expansion of mold that would make respiratory coverage mandatory for access to construction.
The state of construction made it almost unlikely to be painted in some areas, so it was mandatory for the facility to be incredibly critical before it could be demolished, requiring extensive characterization efforts to locate the uranium deposits left in the procedure pipes. because the installation was not tightly closed and the procedural pipe was not purged as it deserved.
Second, the large length of fuel diffusion facilities presented unique challenges, not only with the demolition and shipping facets of labor waste, but also in specific deactivation activities. Due to the repetitive nature of the process, the same deactivation activities were carried out literally thousands of Whether you separate compressors from their engines, cut and obstruct converters and a measure of other deactivation activities, those responsibilities have happened thousands of times. Repetitive task research is sometimes related to production processes and not to D
Process improvement groups analyzed a variety of responsibilities and discovered tactics to improve power by saving one or two hours according to the set of activities. While this might seem negligible, if this set of activities is repeated 6,000 times, the result is a saving of 3 to six years of work.
The third challenge was waste volumes. Once demolition begins, it becomes clear that effective waste disposal is paramount. Fortunately, Oak Ridge has a mobile disposal device on site and, more fortunately, a transport direction of 11 km from the K-25 site to the environmental area. Waste Management Facility (EMWMF) near the Y-12 National Security Complex. To streamline the process, we have developed a state-of-the-art RFID [Radio Frequency Identification] formula to help track and manage trucks and knowledge of the waste to be as it should be We also use a ‘pack on the fly’ technique for management waste, which prevented infected waste from accumulating and causing greater danger to personnel and the environment.
The Fourth Technicium-99 Challenge [Tc-99]. The Tc-99 is a low-energy beta emitter that is water soluble. Some of the gas dispersion devices and parts of the construction structures became infected with Tc-99. Approximately 88% of the total volume of Tc-99 eliminates you on-site in EMWMF. UCOR also oversaw the design of a reusable container that can accommodate giant compressors. This innovation has stored the allocation of K-25 over $1 million.
POWER: Were there positive surprises in the project, such as responsibilities that were made more smoothly than expected?
Rueter: With the exception of the availability of on-site waste disposal, a compromised shipping route, we would find it difficult to identify the “positive surprises” that made the final touch of the project less difficult than expected.
By drawing up plans and allocating resources, UCOR was able to complete the ETTP engraving (Figure 2) 4 years before the DOE schedule, saving taxpayers approximately $80 million, while avoiding $500 million in environmental responsibilities.
POWER: How many staff members were interested in the project?What experience was important to success?
Rueter: Without a doubt, it is the key to our success. When they meet, the skills and talents of those staff shape an exclusive team with varied backgrounds and disciplines that, if dissolved, would be difficult to replicate. Combined and well-implemented and managed, the existing team creates an unprecedented force channeled towards achieving goals and visions that serve important national interests and set the level for additional cleanup progress in the coming decades.
UCOR is 45% higher since its contract inception in 2011. UCOR has approximately 1,800 workers committed to its Oak Ridge mission, compared to 1,248 in 2011. During the same period, Congressional investment increased from $ 420 million to $ 646 million consistently. with year.
UCOR’s is a specialized team of professionals, ranging from engineers and accountants to construction mechanics, carpenters, electricians, chemical operators, rigging agents, appliance operators, waste control specialists and more, many of them come from North American structure unions and atomic trades. and Labor Council. They were all essential for the good luck of this project.
POWER: Is there anything else you would like to give a percentage on the project?
Rueter: UCOR has a rich history of completing projects earlier than scheduled and under budget, speeding up the cleaning years. Until 2020, UCOR’s highly professional has completed the following:
We have an exemplary history of protection. In 2019, UCOR named one of the safest corporations in the United States through EHS Today magazine, detecting its most productive practices that go beyond meeting regulatory requirements. In addition, we have twice gained the status of DOE’s VPP Star, which is the highest popularity of a culture of protection granted through the Department. The prize awarded in 2015 and will be collected in 2019.
Without ever losing the mission, UCOR has invested a lot of time, cash and volunteer hours in the community. A key goal has been the progression of the long-term workforce. For example, in 2016, UCOR led the creation of a new minor in nuclear dismantling and environmental control at the University of Tennessee for its nuclear engineering department, the first of its kind in the United States.
Completion of the cleanup will reduce hazards to workers, the public, and the environment, while allowing cleanup resources to continue the transition to the eastern component of Oak Ridge Reserve: Oak Ridge National Laboratory and Y-12 National Security Complex. it will also leave a thriving multifunctional shopping park, a national park and a conservation area.
Aaron Larson is the editor-in-chief of POWER (@AaronL_Power, @POWERmagazine).
The debate on the role of nuclear power in electricity generation continues as it revolves around climate change . . .
POWER in 2018 reported on the lasting effect that a decrease in educational programs has had on the . . .
The increase in distributed or decentralized electricity generation has been supported through urban energy, production from installations . . .
Reliability and resilience are hot words in today’s world of power generation. The emphasis is on your assessment . . .
© 2020 Access Intelligence, LLC – All rights reserved